FARCROSS project has been featured in IPTO’ s magazine as well as at the workshop that was organized by Systems Operators Committee and Research Development and Innovation Committee.
You can read the magazine here

Aim of the OPTIM-CAP demo is to optimize the usage of the available transfer capacities for reserve procurement and for energy trading, building on top of the current auction algorithms, thus assuring the system security and the more effective allocation of the grid capacity. Preliminary design for the co-optimized market was developed, with detailed functionality, energy-reserve market timeline, gate closure synchronization. The gap between the current transmission right allocation methods based on energy schedules (order collection, clearing, allocation, settlement) and the procurement of frequency ancillary services (order collection, dispatch, procurement, awarded capacities) was identified. Energy producers and market operators have elaborated potential solutions to link energy and capacity bids on the market.

The WAMS Demo is the subject of WP6: Implementation of a Wide-Area Protection, Automation and Control system (WAMPAC) applied to Cross-Border Transmission Systems.

The first Task of WP6 deals with preliminary studies that are needed previously to the deployment of WAMPAC DEMO.

T6.1 works in different lines:
– Analysing, using Digsilent software, the dynamic model of Greek network with the aim to:

  • Know the best location of PMUs for the DEMO
  •  Reproduce oscillations

– Analysis and assessment, using MATLAB, of different methods for detecting oscillations: Prony method, Matrix Pencil, Least Squares…
– Joint analysis of the previous two points to detect the oscillations generated in the model with the methods developed is in process.
– Initial tests have been applied in CIRCE laboratory with real PMUs and PDC:

  • Connection of RTDS with GTNET PMU card to PDC in laboratory
  • Connection of PMU in laboratory with the PDC using c37.118 protocol

The DRL-H DEMO is the subject of WP5 with the general aim to implement a complex grid management technology for handling cross-border transmission line capacity-related issues. In the first semester, the main goal was to prepare the sensor installation to ensure the data collecting in the demonstration part of the project. FARCROSS partners have teamed up and reached the following milestones:

Selection of transmission line

To achieve a unified system in power line selection, a novel multi-criteria-based system was established. This system contains all the important information based on which the optimal overhead-lines can be selected to implement the dynamic line rating (DLR) system. This criteria system considers the absolute and relative curves of the power lines, the restrictive elements of the line, strategic plans in the regions, and historical events from the last few years. Based on the multi-criteria system, each TSO (APG, HOPS, MAVIR, NOSBiH, IPTO) determined on which power lines they need to build up the DLR system first.

Figure 1 Demonstration places in WP5

Figure 1 Demonstration places in WP5


 
Selection of sensor installation place

For the selected power lines all the technical, geographical, and historical data were collected to do the simulations for the critical span analysis. As a result of this process, a unified system has been developed that considers the sag position of the lower phase conductors. Based on the extent of the clearance level, the TSOs can define the so-called critical spans, where the sag problems due to thermal issues can occur first. This is an important part in the preparation, due to these critical spans determines the installation places of the sensors.

Figure 2 Critical span analysis for the selected power line

Figure 2 Critical span analysis for the selected power line

 

Figure 3 Critical span analysis for the selected power line

Figure 3 Critical span analysis for the selected power line


 
DLR sensor testing preparation

The project team with the cooperation of the sensor manufacturer companies (C&G, MONITECH) determined those critical laboratory tests that need to be performed on the sensors applied in the demonstration part of the project. These tests are important to find out whether there is any mechanical, electrical, or other type of stresses that could affect the proper work of the devices.

FARCROSS project was presented in the Bridge newsletter #9.

To read the newsletter please visit the link by clicking here

The EuroPan Demo is the subject of WP7  with the goal to produce improved system operation planning/forecasting and analysis tools – on the inter-TSO level. The effort starts from the capability of the FARCROSS partners to derive accurate weather forecasting at a high level of spatial resolution, such that models of RES generation and load forecasting reach high accuracy results. These model-predictions of power are then fed as input to power flow analysis tools to support TSO operation and cross border collaboration.

Figure 1 Determining the appropriate spatial resolution according to the geography (oreography) under investigation

Early on, the FARCROSS partners have teamed-up to start the system design and the analysis of requirements, while working in parallel on the technical implementation and the data needed for the model parameter tuning and simulation results’ validation.

The weather forecasting results are already under comparison with existing historic data – several months ahead of schedule – to determine the appropriate model parametrization for given geographic idiosyncrasies. Additional data are collected from the responsible TSOs on specific Points of Interest to trim the model parameters on the areas with a real-life interest.

Figure 2 Comparison of real-data vs. wind predictions (for 2018) in the form of wind roses for the area of Debrecen (Hungary)

LineVision, Inc. recently announced its expansion into Europe and a partnership with the European Commission-funded FARCROSS consortium. The company will work with four FARCROSS utility participants in Hungary, Greece, Slovenia, and Austria to deploy advanced sensors and analytics for transmission line monitoring.

For more information read here